Johnstown Community YMCA Project Updates

The Town of Johnstown closed on the Mountain View property, home of the Johnstown Community YMCA, on January 16, 2018. The project is currently in the design phase, which will conclude in August 2018. The construction phase, which is anticipated to take 14-16 months to complete, will commence in October 2018. The recreation center is anticipated to open in late 2019/early 2020.

_________________________________________________________________________________________

UPDATE: 7-26-18

Weld County Road 46.5 (Centennial Drive), adjacent to the Mountain View West development, got its first lift of asphalt paving.

Centennia Dr Asphalt Paving
Centennia Dr Asphalt Paving
Centennia Dr Asphalt Paving

____________________________________________________________________________________________
UPDATE: 7-9-18

Crews began paving streets in the Mountain View West development.

Paving Streets in Mountain View West Development

____________________________________________________________________________________________
UPDATE: 7-3-18

During a work session following the July 2, 2018, Town Council meeting, representatives from Perkins & Will, project architect, presented digital drawings showing the exterior elevation of the Johnstown Community YMCA. Those drawings are provided below.

Rendering - Johnstown Community YMCA-Entry
Rendering - Johnstown Community YMCA - View from Parish Ave.

____________________________________________________________________________________________
UPDATE: 6-15-18

Crews startedinstalling curb and gutter in the Mountain View West development.

Installation of curb and gutter in Mountain View West development
Installation of curb and gutter in Mountain View West development
Installation of curb and gutter in Mountain View West development
Installation of curb and gutter in Mountain View West development

____________________________________________________________________________________________
UPDATE: 6-5-18

Following the June 4, 2018, Town Council meeting, Councilmembers met with Perkins & Will Architects during a work session to receive an update on the Johnstown Community YMCA. Architects provided drawings of the facility’s design, which are provided below.

design drawings 1
design drawings 2
design drawings 3

____________________________________________________________________________________________
UPDATE: 4-27-18

Pictured below is the installation of the new water main in the Mountain View Development at Centennial Drive (Weld County Road 46.5).

Photo of installation of new water main at Mountain View development at Centennial Drive
Photo of installation of new water main at Mountain View development at Centennial Drive

____________________________________________________________________________________________
UPDATE: 4-16-18

During the regularly scheduled April 16, 2018 Town Council meeting, Adolfson & Peterson Construction was approved to perform Preconstruction Services for the Johnstown Community YMCA Project.

____________________________________________________________________________________________
Pictured are Connell Resources construction crews installing storm water pipe in the Mountain View West Development. These photos were taken on April 4, 2018.

construction workers installing storm water pipe in the Mountain View West Development.
photos of Connell Resources construction crews installing storm water pipe in the Mountain View West
photos of Connell Resources construction crews installing storm water pipe in the Mountain View West
Another photo of storm water pipe being installed

____________________________________________________________________________________________
UPDATE: 2-22-18

The following is the list of firms that submitted proposals for the community recreation center.

  • Adolfson Peterson
  • Alliance Construction
  • Fransen Pittman
  • JHL Construction
  • PCL Construction
  • Pinkard Construction
  • Saunders Construction

____________________________________________________________________________________________
Pictured are construction crews installing sanitary sewer pipe and related manholes in the Mountain View West Subdivision. These photos were taken on February 14, 2018.

3 - 3
2 - 2
1 - 1

____________________________________________________________________________________________
UPDATE: 2-12-18

The Town of Johnstown sent out a Request for Qualifications (RFQ) for Construction Manager/General Contractor for the Town’s new recreation center on January 25, 2018. The Town received eight responses to the RFQ from the following contractors listed below:

  • I2
  • Adolfsen Peterson
  • Alliance Construction
  • Fransen Pittman
  • JHL
  • PCL
  • Pinkard
  • Saunders

Request for Proposals (RFP) were sent to each of the contractors on February 12, 2018.

____________________________________________________________________________________________

The developer hired a contractor to begin site work in anticipation of development of their property and the recreation site. The following photos of site preparation work were taken on January 11, 2018.

moving ground 6
moving ground 5
moving ground 2
moving ground 4
moving ground 1
moving ground 3